Sign In
Sign Up
Sign Up
Sign In
Email :
Password :
Forget Password
Enter your email to reset the password
Full Name :
Email :
Password :
Re-type Password:
Country:
Account Exists
Your account has been shared, sign in now
We have Found an existing account with
,
If you're owner of the account you can share that account with
, by accepting our
.
Email
Password
Home
Login/Register
About Us
Contact Us
Home
Categories
Companies
Top Rated
Recently Added
Beat High Score
By Category
By Company
Users
Home
»
Categories
»
Time and Work
»
If 6 men and 8 boys can do a piece of work...
If 6 men and 8 boys can do a piece of work...
2
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
a.
4
b.
5
c.
6
d.
7
Asked By :
subramanian
Categories :
Time and Work
,
Numbers
Answer:
a. 4
Post Your Answer
Previous Question
Next Question
Related Questions
If 13 men can complete a piece of work in 36 days, then in how many days will 18 men complete the same work?
Andy and Brito can finish a piece of work in 10 days, Brito and Cate in 20 days and Cate and Andy in 30 days. How many days would Andy take to complete the work?
A company contracts to paint 3 houses. Mr.Brown can paint a house in 6 days while Mr.Black would take 8 days and Mr.Blue 12 days. After 8 days Mr.Brown goes on vacation and Mr. Black begins to work for a period of 6 days. How many days will it take Mr.Blue to complete the contract?
Two trains each 100 m long, moving in opposite directions, cross each other in 8 seconds. If one is moving twice as fast the other, then the speed of the faster train is
Two trains starting at the same time from two stations 200 km apart, and going in opposite directions cross each other at a distance of 110 km from one of the stations. What is the ratio of their speeds?