A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

  1. 12
  2. 14
  3. 10
  4. none of these
Asked By : SubramanianCategory : Time and Work
Answer
c. 10